EPCIC of PL429 & PL430 Pipeline Replacement Project, Petronas Carigali Sdn Bhd

2020 – 2021

Equipment Coke Drum (2 unit Only At Malaysia)

MRCSB V-32201 (PMT 111743) & V-32202 (PMT 111744) Circumferential Weld Repair For Internal & External by Welding With PWHT

Equipment Coke Drum (2 unit Only At Malaysia)

15 October 2020-31 January 2021

CF Renewal F51202 Activity At MRCSB Melaka July-Dec 2020

Supply and Delivery of Check Valves, Solar Alert Murphy Oil Co. Limited, 2018 

Supply And Delivery of Gate, Globe and Check Valves, Sapura Energy, 2018

To Supply Materials, Consumables, Labors, Testing And Quality Inspection & Control For The Construction of 1 unit Sodium Hypochlorite Injection Skid for GascoTaweelah Gas Compressor Station Project, Sodium Hypochlorite Skid with GRVE Pipes & Tank,I M Kinetic Asia Pte Ltd, 2017

To Supply Materials, Consumables, Labors, Testing And Quality Inspection & Control For The Construction of 1 unit Chemical Injection Skid with Corrosion Inhibitor & Biocide for GascoTaweelah Gas Compressor Station Project, Corrosion Inhibitor & Biocide Skid, I M Kinetic Asia Pte Ltd, 2017

To Supply And Delivery To Site of Caisson Pump For PCSB SEPAT PHASE 2A Project, Air Operated Double Diaphragm (AODD) Pump with Hastelloy C Material, MMHE Sdn Bhd, 2017

Portable Injection Pump Skid (Glycol) for ExxonMobilGuntong EOR Early WAG Project-Guntong C, Chemical Injection (CI) Skid, Woodgroup Engineering Sdn Bhd , 2017

Supply Of Two (2) Units Chemical Injection Pumps (Gas Driven) For SKO D21JT-A – Workover Campaign Scope – Pour Point Depression Package (PPD), Dayang Enterprise Sdn Bhd, 2017

Supply Of Two (2) Units Chemical Injection Pumps (Gas Driven) For SKO D21JT-A – Workover Campaign Scope – Corrosion Inhibitor Package (CI), Dayang Enterprise Sdn Bhd, 2017

To Supply And Deliver Chemical Injection System And Tote Tanks for SKG F12-JT Project, Corrosion Inhibitor Skid, MMHE Sdn Bhd, 2016/17

To Supply And Deliver Chemical Injection System And Tote Tanks for SKG F12-JT Project, Methanol Skid, MMHE Sdn Bhd, 2016/17

To Supply And Deliver Chemical Injection System And Tote Tanks for SKG F12-JT Project, 6 Units of Tote Tanks with DNV approval, MMHE Sdn Bhd, 2016/17

Supply and Delivery of Manual  Valves  Tote Tanks for SK310 B15 Development Project, Sapura Energy, 2016/17

Supply and Delivery of API 10K Valves for SK310 B15 Development Project, Sapura Energy, 2016/17

To Supply And Deliver Portable Water Pump for SKE SK310 B15 Development Project, ITTGoulds Centrifugal Pump, SapuraKencana HL Sdn Bhd, 2016

Portable Air Driven Pump for Engineering, Procurement And Construction (EPC) Of Wellhead Platform ForRepsol OilKinabalu Redevelopment Project, Air Operated Double Diaphragm (AODD) Pump Skid, OceanMight Sdn Bhd, 2016

To Supply And Deliver Open Drain Caisson Pump for SKE SK310 B15 Development Project,Air Operated Double Diaphragm (AODD)with Hastelloy C Pump Material Skid,SapuraKencana HL Sdn Bhd, 2016

Servicing Of Steam Coil Air Heater (SCAH) and BOP Condensate Pump During Planned Outage (30th August – 8th October 2016) For GF2 Boiler Maintenance Section At Stesen Janakuasa Sultan Azlan Shah, Janamanjung. ITT Goulds Pump, 2016

To Supply, Delivery, Installation and Commissioning To Ranhill Powertron, Sepanggar Bay (Kota Kinabalu, Sabah) of Cooling Water Pumps (Closed Loop) For Gas Turbine 11 Upgrading Project, KSB MCPK (non-API) Pump with SS316 Material, 2016

Provision of Supply, Delivery, Install, Testing and Commissioning of Four(4) Units of Polymer Preparation Skid complete with Tank for Sohar Refinery Improvement Project, SIEMENS Singapore, 2015 /16

Supply And Delivery of DBB Valves for Guntong EOR Early WAG Project, Wood Group and ExxonMobil, 2015 /16

Repair, Testing & Commissioning of API 676 Progressive Cavity Pump for Sump Pit – GPP-B PETRONAS Gas Berhad, 2015

Provision of Supply and Delivery of Chemical Injection Skid, Chemical Injection Pump and CI FEED Tank for TAPIS E Platform, Sapura Kencana HL Sdn Bhd , 2015

Provision of Supply, Delivery, Testing and Commissioning of One (1) Unit of OHD Caisson Pump for MURPHY SASA Platform , Bumi Jaya Engineering Sdn Bhd, 2015

Provision of Supply, Delivery, Install, Testing and Commissioning of Four(4) Units of Chemical Injection Skid complete with Partitioned Tank for MISC MAMPU Project, NGL Tech Sdn Bhd, 2015

Provision of Supply, Delivery, Install, Testing and Commissioning of Two(2) Units of Chemical Injection Skid complete with Tank for Murphy South Acis Satellite (SASA) Topsides Project, Brooke Dockyard, 2015

Provision of Supply, Delivery, Testing and Commissioning of One (1) Unit of Closed Drain Pump for TALISMAN Bunga Rya Platform , Bumi Jaya Engineering Sdn Bhd, 2015

To Rent And Deliver of William Pump Skid, Chemical Injection Skid with complete set (CI Skid),ScomiSosma Sdn Bhd, 2015

Supply and Delivery of On/Off Valve to Dew Point Control Unit 2 (DPCU2) for Plant Revamp & Rejuvenation 4 (PRR4), PETRONAS Gas Berhad / Toyo Engineering & Construction Sdn Bhd, 2013/14

Provision of N2 Generator Package, Pakistan Refinery Limited, 2013

Provision of Supply, Delivery, Install, Testing and Commissioning of Two (2) Units of Nitrogen Generators at Labuan Gas Terminal-2 (LGAST-2), Petronas Carigali Sdn Bhd – Sabah Operation (SBO), 2012/13

Design, Supply of Materials, Manufacture, Test and Delivery of Air Compressor and Air Dryer Package for KPOC Topsides, Malaysia Marine and Heavy Engineering Sdn Bhd, 2011/12

Supply, Testing & Commissioning of Cryorgenic On/Off Butterfly Valves and Motorised ESD Ball Valves for LNG Regasification Unit (LEKAS), PETRONAS Gas Berhad / Ranhill Worley Parson, 2011/12

Design, Supply, Deliver, Testing & Commissioning of Air Compressor and Air Dryer Package for the LNG Regasification Unit (LEKAS), Petronas Gas Berhad / Ranhill Worley Parson, 2011

GF3 Conveyor Structure restoration works at Sultan Salahuddin Abdul Aziz Power Station, Kapar, Kapar Energy Ventures Sdn Bhd, 2010

Corridor Project Erection of Piperacks and Installation of All Utilities Interconnections, PETRONAS Chemicals Methanol (Labuan) Sdn Bhd, 2009/10